Project Detail |
The Michigan Department of Transportation (MDOT) is investing about $9 million to rebuild overpasses, including deck replacement, bearing replacement, substructure repairs, beam end repairs, steel cleaning and coating, and approach work on I-75 at Cheeseman Road in the city of St. Ignace, Mackinac County. This project is scheduled to be completed in two years, with work on northbound I-75 to be completed in 2025 and southbound I-75 in the 2026 season. No work will occur during winter shutdown periods. County: Mackinac Highway: I-75 Closest City: St. Ignace Start date: Monday, March 31, 2025 (tentative) Northbound and southbound I-75 traffic will be reduced to one lane, with northbound traffic crossed over to the southbound side using temporary crossovers. Two-way traffic will be maintained via temporary concrete barrier walls. A 12-foot lane width restriction will be in place during the project. The posted speed limit will be reduced to 60 mph; 45 mph where workers present. |