Construction of flood berms throughout the Drumheller area, including the Midland, Newcastle, Willow Estates, and Grove Plaza all beginning in 2022, with Downtown flood berms beginning construction in 2023. Additional areas are planning for berm construction in 2023 and 2024.
The Government of Alberta announced $27.3M in additional funding for the project on March 23, 2023.
Municipality: Drumheller
Sector: Infrastructure
Type: Flood Mitigation
Schedule: 2022 - 2024
Estimated Cost: $81.5M
Stage: Under Construction
Developer: Town of Drumheller
Contractor: Multiple |