In summer 2023, contractor crews will begin work to improve the northbound I-5 North Fork Lewis River Bridge deck, just south of Woodland, Washington. Work on the bridge will include deck repairs, placement of a polyester concrete overlay, expansion joint modifications, and new joint seals. In summer 2024, contractor crews will begin work to improve the southbound I-5 North Fork Lewis River Bridge deck. Work will include removal of the existing asphalt overlay, deck repairs, placement of a polyester concrete overlay, expansion joint modifications, new joint seals, replacement of the approach slab on the south end of the bridge, and repairs to mitigate cracking of several steel beams. Timeline Spring 2023 - Fall 2024 Project status Pre-construction Funding The cost of this project is estimated at approximately $17.4 million |