Project Detail |
Project Development Objective
PDO Statement
The proposed project development objectives are to increase access to and quality of water supply
services, and to improve the operational performance of the water supply services provider, in South Tarawa.
PDO Level Indicators
PDO indicators for the proposed project include:
(a) People provided with access to improved water sources through piped house water connections
(male/female)
(b) People provided with continuous water supply (male/female)
(c) Samples testing at distribution points meeting national standards for residual chlorine (%)
(d) Non-revenue water (%)
(e) Time spent daily by households collecting water (minutes)
B. Project Components
To achieve the Project Development Objectives (PDOs), the proposed project will have five components.
Annex 2 provides a detailed project description. The table below describes project costs by component and
provides the financing plan with contributions of the various stakeholders. The project will be cofinanced with
ADB and the Green Climate Fund (GCF), 25 and will include a counterpart financing contribution. The GCF grant will
be administered by ADB as an accredited entity of the GCF. All three sources of financing will be made available
and implemented in parallel, throughout the eightyear implementation plan.
Component 1: Improvement of Water Supply Services (Cost: US$30.28 million excluding contingencies;
Financing: IDA – US$7.44 million equivalent, ADB and GCF – US$22.09 million and Counterpart financing –
US$0.75 million) |