Project Detail |
Project Description The single block 150MW Coal Fire Power Plant using subcritical CFB boiler technology was constructed adjacent to the existing operational 2x50MW Coal Fired Power Plant. The site is located in Sihanoukville, Cambodia. The project was procured with GE boiler and turbine and delivered by TPSC as EPC. The project has Commercial Operation in November 2019. Services Owners Engineering Services · Tender preparation, EPC bidding and contract award · Design review; project management, EPC contract administration · Factory acceptance tests, and engineering review · Site supervision services including construction, erection, commissioning monitoring, and testing activities. · Independent Engineer Services for the Lenders. |