Project Detail |
CORRIDORS MANAGEMENT PLAN FOR
THE RING OF GROWTH IN WEST AFRICA (WAGRI-CACAO)
1. TITLE: Construction Project of the Grand Bassam-Aboisso-Frontier Highway of Ghana
2. COUNTRIES OF INTERVENTION: COTE DIVOIRE
3. AREA OF INTERVENTION: SOUTH / SOUTH EAST
4. AREAS OF INTERVENTION: ROADS AND WORKS OF ART
5. STRATEGIC AXIS OF THE MASTER PLAN: Button B: Integration of the coastal market
6.JUSTIFICATION OF THE PROJECT:
The development and asphalting of this 136-km long 2x2-lane highway with a central reservation is essential to ensure and amplify the commercial exchanges and the displacement of the populations of all the coastal capitals located on the Abidjan- Lagos. This axis is a priority route for ECOWAS and is part of the African Union Highway projects (TAH 7) linking Dakar to Mombassa via Abidjan and Accra.
7. MAJOR STAKEHOLDERS
Project Manager: MINISTRY OF ROAD EQUIPMENT AND MAINTENANCE
Project management: PRIVATE PROVIDER
Beneficiaries: STATE OF COTE DIVOIRE / POPULATION AND TERRITORIAL COLLECTIVITIES
Other stakeholders: DGIR / AGEROUTE / FER / LBTP
Coordination and monitoring and evaluation AGEROUTE
8. STRATEGIC DIRECTIONS
General Objective (Goal): Contribute to the development of trade along the corridors and with Ghana and Togo.
Specific objectives: 1. Construction of a Highway
2. Improving the incomes of indigenous peoples
3. Improvement of the population safety index
Expected results :
(Deliverables and effects) 1. Built motorway
2. Population standard of living improved
3. Reduced safety index
Main activities :
1. Earthworks
2. Road works
3. Realization of hydraulic works and sanitation
4. Related Facilities (Schools, Markets, Road Toll Station, Weighing Station, etc.)
Environmental and social impact: Conduct of environmental and social impact studies to assess the impact of the project on populations, their property and vegetation
9. FINANCING PLAN
Estimated cost of the project: 408,000,000,000 CFA Francs
Amount mobilized: 0 CFA franc Rate: 00%
Source Amount Financing instrument
(PPP, State Budget, Loan, Other)
F CFA USD
State:
Private promoter:
Development partners: 408,000,000,000 741,818,181.81 Loan
Private partners:
Remaining to be mobilized: 408,000,000,000 741,818,181.81 Rate: 100%
10. DURATION - MAIN STAGES OF THE PROJECT
Estimated completion time 5 years Start: 03/2020 End: 03/2025 |