Project Detail |
Component 1 — Investment in Water Supply Infrastructure: Construction and rehabilitation of well fields and
intakes, main water lines, water treatment facilities, pumping stations and distribution networks.
• Component 2 — Investment in Sewerage Infrastructure: Construction of centralized sewage systems in district
centers consisting of collectors, pumping stations and biological sewage treatment plants as well as discharge
facilities. Extension of sewerage network in Bukhara City.
• Component 3 — Capacity Building and Implementation Support
o Component 3a — Capacity Building: Improving business practices of Bukhara Suvokova with regards to
Asset Management, Operation and Maintenance, Client Management and Complaint Handling, Billing and
Collection. The areas of capacity building will be further defined and agreed during preparation based on the
client’s needs.
o Component 3b — Project Implementation and Management Support: Project management and
implementation support to assist the Implementation Agency (IA) in ensuring seamless coordination, efficient
implementation and compliance with the relevant policies.
Objective The project objective is to provide access to safe, reliable and affordable water and sanitation services in the Bukhara
region
Financing Plan for Phase I:
Project cost:
AIIB loan:
GoUz:
USD 422 million
USD 357 million (85%)
USD 65 million (15%)
Financing Plan for Phase II:
Project cost:
AIIB loan:
GoUz:
USD 236 million
USD 200 million (85%)
USD 36 million (15%)
The above phases will be approved as two separate projects. |