Project Detail |
Project Karot Hydropower Station Primary Energy Input Hydel Technology Hydel Installed Capacity (MW) 720 Location River Jehlum Province AJK / Punjab Estimated Cost (US $ Million) 1698.26 Executing Company / Sponsors Karot Power Company Ltd. (KPCL) / CSAIL/ CTGI /CTG (China Three Gorges) Financing Independent Power Producer (IPP) Coordinating Ministry Ministry of Water and Power Supervising Agency Private Power and Infrastructure Board (PPIB) Project Progress Update Land acquisition award done. Financial Close achieved on 22nd February 2017. Construction of access road/bridge, concrete batching plant, diversion tunnel and spillway, etc. are in process. Work initiated through equity – 41% civil works completed. Expected Commercial Operation Date (COD) December 2021. |