Project Information PIN: 009005B As of date: November 2018 Region: Capital Facilities Regional Admin: M. Smith State Route: I-90 Current Status: Pre-Construction Legislative Districts: 13 Project Description The septic system services both the east and west bound Ryegrass Safety Rest Areas. During a site visit, evidence of a drain line blow-out and surface ponding of effluent was visible. Upgrade the current system into a sewage lagoon type system to meet safety standards. Project Milestones Milestone Original Date Current Date Status Project Definition Complete Preliminary Engineering Start Q3 2016 Q3 2016 On Schedule Environment Complete Q2 2017 Q2 2017 On Schedule Right of Way Complete Contract Advertisement Q3 2021 Q3 2021 On Schedule Operationally Complete Q1 2022 Q1 2022 On Schedule Project Cost Summary($ in thousands) Project Status Leg. Initial Budget Current Leg. Budget Current Approved Cost Preliminary Engineering $0 $402 $234 Right of Way $0 $0 $0 Construction $0 $5,041 $2,066 Total: $0 $5,443 $2,301 |