Project Detail |
Project Information
PIN: 000532F As of date: November 2018
Region: Capital Facilities Regional Admin: M. Smith
State Route: I-5
Current Status: Construction Legislative Districts: 21, 38
Project Description
The RV dump station heater is not working properly. The current connection is not adequate. Upgrading the site electrical service by modifying the PUD service and supplied power, replace existing cabinet, and reconnect services will allow the RV dump station slab heater to work properly.
Project Milestones
Milestone Original Date Current Date Status
Project Definition Complete Q3 2018
Preliminary Engineering Start Q3 2018 Q3 2018 On Schedule
Environment Complete
Right of Way Complete
Contract Advertisement Q3 2018 Q3 2018 On Schedule
Operationally Complete Q1 2019 Q1 2019 On Schedule
Project Cost Summary($ in thousands)
Project Status Leg. Initial
Budget Current Leg.
Budget Current Approved
Cost
Preliminary Engineering $0 $25 $25
Right of Way $0 $0 $0
Construction $0 $101 $101
Total: $0 $126 $126 |