Project Detail |
Project Type: Civil & Industrial Buildings (Water/Wastewater Treatment) | Procurement Type: Bid-Build
State: Georgia | Status: Ongoing
Overview:
Originally constructed in 1964, the WRF is due for upgrades to its critical process treatment equipment. Once completed, these upgrades will increase the plant’s resiliency by replacing critical systems, making the plant less susceptible to high flows during heavy storm events.
Technical Details:
The project’s major elements include:
replacement of three 350 HP influent pumps and associated piping, valves, instrumentation and controls
replacement of 4 turbo aeration blowers and associates piping, valves, instrumentation and controls
replacement of two 100-foot diameter sludge digester covers
The work also includes:
temporary bypass pumping of all the plant’s influent flow (84 million gallons per day)
replacement of digester boilers and associated piping
lowering of the existing aeration diffusers located in the aeration basins
installation of two new isolation valves in the existing influent discharge piping to eliminate the need for future bypass pumping operations |