Project Detail |
US 2/Eagle Falls Vic to Tye Creek - Bridge Decks Overlay Top PIN: 100231C Current Status: Pre-Construction Regional Admin: M. Cotten Project Milestones Milestone Original Date Current Date Status Contract Advertisement Q4 2019 Q4 2019 On Schedule Operationally Complete Q3 2020 Q3 2020 On Schedule Project Cost Summary ($ in thousands) Leg. Initial Budget Current Leg. Budget Current Approved Cost Total: $0 $2,679 $2,545 Region: Northwest As of date: November 2018 State Route: US 2 Legislative Districts: 39 Project Description Remove the existing overlay deck, place new HMA, and modify the transverse joint seal and expansion joints/headers at some bridges within project limits. Crack sealing, HMA saw cut and seal, and extruded curb and energy dissipation pad installations will also be performed on some other bridges. |