Project Detail |
I-5/Custer SB SRA - Sewer Line Replacement - NWR Top
PIN: 000537C Current Status: Pre-Construction Regional Admin: M. Smith
Project Milestones
Milestone Original Date Current Date Status
Contract Advertisement Q1 2028 Q1 2028 On Schedule
Operationally Complete Q3 2028 Q3 2028 On Schedule
Project Cost Summary ($ in thousands)
Leg. Initial
Budget Current Leg.
Budget Current Approved
Cost
Total: $0 $1,610 $1,434
Region: Capital Facilities As of date: November 2018
State Route: I-5 Legislative Districts: 42
Project Description
There has been an increased use of the rest areas since the sewer was designed in 1980. The Ferndale Sewer has now been extended closer to the rest area. We presently maintain 6.4 miles of 2" and 3" pressure PVC sewer line that requires frequent maintenance that serves both the SB and NB rest areas. Installing a new sewer line to that will intercept the municipal sewer closer to the rest area will meet the higher demand, reduce sewer maintenance, and improve reliability. |