Project Objective and Expected Results
The objective of the Project is to increase the reliability and stability of gas supply by expanding gas
storage capacity and the expected result is improved energy security.
III. Project Description
The Project consists of the following components:
Component 1: Tuz Golu Gas Storage Expansion Facilities consisting of
(i) Surface Facilities: this involves pigging stations, gas transmission lines connecting
to the natural gas grid, all necessary injection and withdrawal units, auxiliaries,
including the compressor facility, filters, fiscal metering units, turbo compressor units,
reciprocating compressor units, water separators, heating and pressure reducing units
and triethylene glycol units;
(ii) Subsurface Facilities: This entails drilling and leaching wells to store gas within the
Tuz Golu area.
(iii) Water and Brine Pipelines: This will involve construction of a fresh water supply
line from the Hirfanli Reservoir to the project site and a brine discharge line from the
wells back to Tuz Golu. This will also include several pumping stations and storage
reservoirs; and
(iv) Electricity Supply: The Project includes electricity transmission lines for water
pumping stations, surface and sub-surface facilities
|