Date: 2017
Contract No: 4400009709
Location: Jeddah, Saudi Arabia
Description:
Nesma Electric has been awarded its first high voltage underground cable project to link the Serafi Mall’s substation to the grid through Jeddah central BSP substation, with an approximate length of 3.4 km. The project scope is to design, supply, install and commission two 110kV underground cable circuits in addition to fiber optic cable from 380/110KV Jeddah central BSP to 110/13.8KV Serafi substation. Besides stabilizing the city electric network, this project is expected to have a great economic impact for the project owner as it will energize the Serafi 110/13.8 kV substation, thereby providing Serafi Mall with a cheaper, more reliable energy source compared to the current standalone generation units. Challenging aspects of the project include the horizontal directional drilling, permitting and traffic control along the route.
Major Equipment:
Testing and commissioning of Two NFOC (96 Cores) & Two circuits of 110kV underground cable in flat formation, using 1x1200mm2 Cu. XLPE Cable per phase, feeding to 110/13.8kV Sarfi Substation Jeddah from 380/110 KV Jeddah Central BSP. The length of each circuit shall be approximately 3.4 Km.
|