Work Detail |
Indian project will involve upgrading electrical substation and constructing double-circuit line Indian company Adani Energy Solutions has won a $325m (Rs2800 crore) power transmission project in Gujarat. The project will supply green electrons for manufacturing green hydrogen and green ammonia in Mundra and will be completed in three years. The work involves upgrading the Navinal (Mundra) electrical substation by adding two large 765/400kV transformers. Additionally, a 75km long 765kV double-circuit line will be constructed to connect this substation to the Bhuj substation. Adani won the project under the Tariff Based Competitive Bidding (TBCB) mechanism and PFC Consulting Limited was the bid process coordinator. This is the company’s sixth order win this fiscal year, taking its orderbook to Rs57,561 Cr. |