Work Detail |
The National Electricity Regulatory Entity reports that this is due to a request from Vientos La Genoveva II, for the San Carlos photovoltaic plant, located in the department of San Carlos.
The National Electricity Regulatory Entity of Argentina, through ENRE Resolution No. 1052/2024, has published the request for access to the electric power transport capacity requested by Vientos La Genoveva II for the entry of the San Carlos photovoltaic park, with 15 MW of installed capacity, located in the department of San Carlos, province of Salta.
According to the resolution, the plant will be linked to the 33 kV medium voltage network of the Argentine Interconnection System (SADI), under the jurisdiction of the Electricity Distribution Company of Salta Sociedad Anónima (EDESA), which will act as an additional provider of the technical transport function.
As is usual in this bureaucratic procedure, the dissemination of the access request is extended for a period of five administrative working days on the ENRE and CAMMESA websites.
Last November, the company Vientos La Genoveva II was authorized to enter this plant as a generating agent of the Wholesale Electricity Market (MEM). |