Work Detail |
National Grid and SSEN Transmission representatives celebrate start of construction at sites in Scotland and England
Groundbreaking has occurred for a 2GW subsea link between Scotland and England.
During the event for the £4.3bn EGL2 project, representatives from National Grid and SSEN Transmission took the first ceremonial spadefuls of earth, marking the start of main construction, at events held at either end of the subsea link in Peterhead in Scotland and Wren Hall in Drax, near Selby in North Yorkshire.
After travelling 436km under the sea from Peterhead, EGL2’s subsea cable will come ashore on the East Yorkshire coast at Fraisthorpe Sands and then run underground for 68km to a new high voltage current (HVDC) converter station at Drax.
At peak periods of construction, the project is expected to support hundreds of local jobs in Yorkshire, through supply chain and construction activity.
Representatives from National Grid were joined in Yorkshire by colleagues from specialist HVDC cable supplier Prysmian, and Hitachi Energy and BAM, responsible for the supply of converter stations at either end of the project, underlining the collaborative spirit and support for the much-anticipated scheme.
Offshore delivery director for National Grid Zac Richardson said: “Today marks an important moment for all involved in the project and the commitment of both National Grid and SSEN in delivering major projects which will play a key role in supporting the UK’s transition to a net zero economy.
“EGL2 is the first of four currently proposed 2GW projects between Scotland and England to begin construction and in total these projects, delivered in partnership by National Grid, could provide enough renewable electricity to power eight million homes.
“Achieving this first milestone wouldnt have been possible without the huge commitment of the project team, our construction partners, stakeholders and the invaluable feedback from local communities.”
Ofgem director general for Infrastructure Group Akshay Kaul said: “Today is a historic occasion. Not only is construction starting on EGL2, Britain’s biggest ever electricity transmission project, but we’re also standing here two years earlier than we might have been thanks to Ofgem’s fast track new process which cuts red tape to get consumers across the country connected to renewable energy more quickly.
“Harnessing homegrown clean energy will help build a secure energy future for Britain, and projects like EGL2 are pivotal in our move towards that.
“This is the first project to successfully complete our new process and many more major energy projects are going through this fast track pipeline.
“Our involvement with EGL2 doesn’t end here we stand poised to step in if needed to ensure maximise efficiency and consumer benefit.”?
Wren Hall Converter Station in Drax (picture of Drax power station in background) has seen the start of main construction activities this month, including site establishment and vegetation clearance.
Surveys are expected to continue along the underground cable route in the coming months.
The project is expected to be operational in 2029. |