BAPCO UPSTREAM W.L.L, Bahrain receives the Bidders proposal to install 7 x NAG Compression stations around Bahrain field.
Following Bidders submitted the proposals:
BEINIT Energy DMCC – BHD 106,520,467.790
JEREH GROUP MIDDLE EAST DMCC – BHD 119,119,031.680
Enerflex Middle East W.L.L – BHD 129,059,384.760
WASCO ENGINEERING INTERNATIONAL LIMITED – BHD 153,666,343.000
ENGINEERING FOR THE PETROLEUM AND PROCESS INDUSTRIES BRANCH ENPPI KSA – BHD 392,920,042.340
The scope will cover the stations only, the interconnecting pipelines from wells and to the receivers will be handled by another contract – in house. Each station will include the equipment: Feed Gas Air Cooler, Inlet Separator, Suction KOD, Compressor & Engine Driver Unit Skids, Discharge Air Cooler, Closed Drain Vessel, Closed Drain Pumps, PA, IA and N2 Package, Chemical Injection Packages, Flare package etc., associated piping, control valves, shutdown valves, F and G, etc. and required Instrumentation and electrical systems. |