The Office of the Executive Engineer, Government of Maharashtra has declared Patel Engineering (PEL) along with its JV partner as lowest bidder (L1) for a contract worth Rs 342.76 crore. The order is to be completed in a period of 24 months.
The said project is located in Maharashtra. The scope of work involves the construction of water lifting arrangement work for LIS 1-10-11-12,8, 9, 3 ,4-5-6 of first stage from submergence of Jigaon project including approach channel, rising main, pumping machinery, switchyard and all allied works of civil, mechanical, electrical component. PEL’s share is 35 percent in the JV.
Patel Engineering has a strong presence in irrigation, tunnels and underground works for hydroelectric and dam projects. PEL have completed over 85 dams, 40 hydroelectric projects, and more than 300 km of tunnelling. Its clinets are mostly central PSUs or state government organisations. |