Procurement News Notice |
|
PNN | 47920 |
Work Detail | 25-year PPA inked with France’s Engie for the project Saudi’s Al-Jouf Agricultural Development Company has awarded a contract to the French multinational utility firm Engie for the construction of an 8-megawatt (MW) solar power project. Construction will start on 20 September 2023, with operations likely to begin on 30 September 2024, the company said in a statement to the Saudi stock exchange on Monday. The plant will be developed for Al-Jouf Agriculturals industrial complex for olive oil and pickles factories and the French fries factory at Busaita. The company also finalised a 25-year solar power purchase agreement (PPA) with Engie. |
Country | Saudi Arabia , Asia |
Industry | Energy & Power |
Entry Date | 04 Sep 2023 |
Source | https://www.zawya.com/en/projects/utilities/saudis-al-jouf-agricultural-awards-8mw-solar-power-plant-n8kztnn2 |