Request For Demo     Request For FreeTrial     Subscribe     Pay Now

Argentina Procurement News Notice - 43370


Procurement News Notice

PNN 43370
Work Detail The opening of the envelopes with the construction companies proposals will take place on July 27. It is the second call for tenders, because the company that had been awarded the work in the first tender resigned. He called for a public tender for the expected building of School 361. The opening of the envelopes will take place on July 27, official sources informed LA ANGOSTURA DIGITAL. In that instance, it will be known how many companies have submitted to the public bidding interested in building the educational establishment. Also, it will be the moment to know the economic offers and if they adjust to the official budget. The official information accessed by LA ANGOSTURA DIGITAL indicates that the official budget set by the provincial government for the work amounts to 520,640,452 pesos at values ??of January 2023. According to official data, the public bidding document determined an execution period of 540 calendar days. The building will have a covered area of ??1,233.65 square meters. The new building of primary school 361 -first stage- will be built on Río Minero street in this town. It will be implanted on a plot of 9,000 square meters, with particular characteristics since it is located on a soil of mallines and with arboreal vegetation of the area. The lot borders Río Minero street and its three dividing axes adjoin different private properties. In the first stage, all the exterior works will be carried out, such as the perimeter sidewalks of the entire building (including the second stage), the playground with its corresponding accesses, the retaining walls, the perimeter fence and municipal sidewalks. The first call for public tenders to build school 316 was made in March of last year. At that time, it was tendered with an official budget of 178,280,258 pesos and the execution period is 540 calendar days. The companies Efede SRL and ABI SRL were presented. It was planned to build seven classrooms, the multipurpose room, the SUM, the administration, the restrooms, the machine room and the playón, Governor Omar Gutiérrez explained on that occasion. However, work could not start because the company that had been awarded the work withdrew from doing it. School 361 arose in 2014 to meet the educational demand in Villa La Angostura due to population growth. The CPE authorized its operation in 2015, but without a building. The educational authorities arranged for the students of 361 to attend classes in other schools in the town. For a time they shared the building with the CFP 24 adult school. Since 2017 it has been operating in the barbecue area and municipal shelter that were remodeled, based on an agreement between the Municipality of Villa La Angostura, which ceded the property on loan, and the provincial government. .
Country Argentina , South America
Industry Construction
Entry Date 28 Jun 2023
Source https://www.construar.com.ar/2023/06/con-un-presupuesto-de-520-millones-la-provincia-volvio-a-llamar-a-licitacion-por-la-primera-etapa-de-la-escuela-361/

Tell us about your Product / Services,
We will Find Tenders for you