Special Economic Authority of DUQM, Oman awards the project, Construction of Dual Carriageway Road for NR 32 Phase 2 at Duqm. The project location is in Al Duqm Waliyat of Al Wusta governate.
Scope of work includes, construction of approximately 12 km of dual-carriageway starting from the end station of NR 32 Phase 1 until the end border of Duqm Authority including 2 Roundabouts, wadi Bridge, 1 km single carriageway service Road.
The main components of the project are as follows
Construction of approx. 12 km of dual carriageways having. 3 lanes on each carriageway with a 12m unpaved median.
Approx. 1 km service roads in front of Existing Filling Station.
Two Roundabouts
One wadi Bridge
Culverts and drainage catch pits,
LED street lighting,
Landscaping.
Relocation & protection of existing utilities and other ancillary works.
Weigh Station (Optional)
Earlier, during January 2021, Oman based construction firm, Premier International Projects submitted the lowest bid. (read more)
The contractor submitted the price of OMR 23,485,850 (USD 61,081,534). |