Work Detail |
On August 12, 2021, the Bidding Newspaper published an article about the receipt of complaints and proposals from contractors about a number of bidding packages invited by Nam Viet A Construction Investment Joint Stock Company for small-scale tenders. , which is simple, has no specific characteristics but sets high and different requirements, limiting the participation of contractors. In which, it is mentioned that the construction contract under the Project of Repairing the Headquarters of the Quang Nam Investment and Development Fund is invested by the Quang Nam Investment and Development Fund (the first bid is expected to be closed on the 20th. August 2021. This bidding package uses the capital of Quang Nam Investment and Development Fund, and is widely auctioned online by the method of 1 phase 1 dossier bag; contract implementation period 90 days, bid security 25 million dong.
On August 18, 2021, Quang Nams bidding inspection and supervision team sent a document to the Investor requesting inspection and modification of the criteria for restricting contractors; extension of time for closing/opening bids; be responsible for resolving the contractors petition to avoid long-term lawsuits and complaints.
Mr. Tran Van An - Leader of Quang Nams bidding inspection and supervision team said that the bidding package to repair the office was small (the package price was 1,726 billion VND) but the bidding consultant and the investor had elaboration, appraisal and approval of Bidding Documents with criteria of capacity and experience that limit contractors, not in accordance with current bidding regulations and guiding and rectification documents of Quang Nam province. For example, the bidding documents require: the contractor must have experience in performing 2 renovation and repair construction contracts; requires 6 key officials, including the site commander, to have a contract to lead at least 2 renovation and repair works; the contractor must have 10 technical workers, 200 sets of scaffolding, matching frames...
On August 19, 2021, Quang Nam Investment and Development Fund sent a document to Nam Viet A Construction Investment Joint Stock Company requesting to implement the contents at the request of the Quang Nam bidding inspection and supervision team.
On August 23, 2021, Quang Nam Investment and Development Fund issued a decision approving the adjustment of the bidding documents for the above bidding package (changing the content of forms 03, 04A and 04B Chapter IV: Bidding and Bidding Forms).
On August 30, 2021, talking to a reporter of the Bidding Newspaper, Mr. Nguyen Ngoc Nhan - Director of Nam Viet A Construction Investment Joint Stock Company said that based on the request of the bidding inspection and supervision team, Mr. Quang Nam, the Procuring Entity has extended the bid closing time and revised the Bidding Documents twice (the first time extending the bid closing time to 7:00 a.m. on August 25, 2021 and the second time extending the bid closing time to 7:00 a.m. on August 27, 2021). .
According to the results of online bid opening, there are 3 bidders submitting bids, including: Joint Venture Huy Hoang Phu Co., Ltd. - Cong Quyen Trading and Construction Company Limited (Bid price 1,254 billion VND, contract execution time 90 day); Ha Dong Construction Joint Stock Company (Bid price VND 1,698 billion, contract execution time 90 days); Nam Duc Dat Construction and Trading Company Limited (the bid price after discounting is VND 1,552 billion; contract execution time is 86 days).
Currently, the bid solicitor is in the process of evaluating bids and is expected to complete the contractor selection in early September 2021 and start construction in September 2021. |