After being bidden by bidder, Ngô Si Liên High School has submitted a report to Dong Nai Department of Education and Training, acknowledging the relocation of the place of sale. The Bidding Documents (HSMT) and affirms the allegedly "pre-tender" images are part of the assignment to repair facilities to serve the 2018 High School National Examination.
The school denies "pre-tender construction"
As the Bidding Newspaper has reported, the package No. 1 under the renovation project Ngo Si Lien High School (Dong Nai), Ngo Sy Lien High School as the investor, Kien Thinh Construction Consulting Company bid solicitor.
In the petition, the contractor reflected at the Ngo Si Lien High School to buy the HSMT, "Guard said that the unit is under construction half a month now and then buy more files." According to the explanation of the school, from 24 to 27/6/2018, the Council of exams work, those who did not fall into the examination. Hence, the respondents representative has met and said that the protection is not actually the schools security guard, but the local defense office to support the exam. The location of the sale of the bidding documents is real because during the above time, Ngo Si Lien High School is the national high school examiner, so the contractors staff to contact the school to buy the bidding documents is not.
Ngô Si Liên High School also asserted that the school organizes the repair of toilets in the test room is as real as reflected by the contractor but in essence is not true. Specifically, after being selected as a national high school exam, the school organized a physical examination and found that the restrooms of teachers and students were damaged, could not be used, the lighting system And fans in some classrooms do not work ... so we have to overcome immediately to serve the exam. On 5/6/2018, the school contracted with the team of mason to repair and repair the damaged facilities mentioned above with the package value of 39.5 million and must complete before the exam. (construction time of 15 days). Due to the weather conditions, the repair lasts so that during the day there are still surplus materials and some repairing sinks on the roof have not been dismantled. According to Ngô Si Liên High School, from this reality, the contractor said that the school has allowed the unsuccessful units to repair works items is not correct. Through this incident, Ngo Si Lien High School also applied for experience in propaganda, implementing the repair of construction in the coming years to avoid misunderstanding.
2/3 bidder bid exceeded
According to Minutes of Bidding Package No.1, there are 5 contractors bidding for bidding documents and 3 contractors submitting bids (Bidding Documents), including: Thanh Nam Construction Consultant JSC, Tu Sa Construction Joint Stock Company and Cong Thanh Tai Construction Trade Services Company Limited with the bid price of VND5,917,515 million, VND5,830,989 million and VND5,790,8669 million, respectively. Meanwhile, the estimated cost / tender package price is VND5,790,867 million. Thus, the bidding price of Thanh Nam Construction Consultant JSC and Tu Sa Construction Joint Stock Company is higher than the bidding package price.
At present, the bidding package price is announced according to the contractor selection plan and must be announced before the bid solicitor announces the selection of contractor. With tender packages funded by the state budget (not ODA loans), investors may only select bidders whose bidding prices do not exceed the bidding package prices. Therefore, if the bidding price is higher than the bidding package price, the contractor will be less likely to convince the bidder not to be bright.
In addition, according to the bid solicitor, Thanh Nam Construction Consultant Joint Stock Company normally submits checks, not checks as required by the bidding documents, thus failing to meet the requirements. This contractor has a certificate of construction capability but only has capacity to operate in the consultancy field and has no capacity for construction of civil works of grade III or higher so it does not meet the requirements of Bidding documents.
TS. Nguyen Viet Hung, a specialist in bidding, said that the reason is not the right and wrong of the requirements stated in the bidding documents, but when the bidding documents "require one way", the contractor will "meet one destination". There is no doubt of public opinion about participating in the "green" for a tender.
|