01.1 1 Psch Setting Up And Clearing The Construction Site02.1 4 Pieces Of Roof Trusses W/H = 18/110-125Cm- Bsh Gl32h - Elevation Wc = 20Mm03.1 90 Running Meters Of Bitumen Primer, Parapet03.2 90 Linear Meters Of Vapor Barrier, Parapet03.3 435 M² Steel Trapezoidal Profile Sheets Sab 158R\/750\/0,8803.4 435 M² Preparation Of Trapezoidal Steel Sheet03.5 60 Linear Meters Of Profile/Bead Filler03.6 435 M² Vapor Barrier, Trapezoidal Sheet Metal03.7 435 M² Thermal Insulation, Trapezoidal Sheet Metal03.8 90 Linear Meters Of Thermal Insulation, Parapet03.9 90 Linear Meters Insulating Wedges, 50 X 50 Mm03.10 435 M² First Layer Of Sealing, Trapezoidal Sheeting03.11 90 Running M First Layer Of Sealing, Parapet03.12 435 M² Second Layer Of Sealing, Trapezoidal Sheeting03.13 90 Running M Second Layer Of Sealing, Parapet03.14 6 Pcs Bitumen Waterproofing, Penetrations03.15 90 M² Parapet Covering Required Item04.1 430 M² Drying Of The Roof Surface04.2 430 M² Subsurface Inspection04.3 430 M² Cleaning Reinforced Concrete Ceiling, Coarse Contamination04.4 430 M² Bitumen Primer, Reinforced Concrete Ceiling04.5 120 M² Bitumen Primer, Attika04.6 75 Linear Meters Of Bitumen Primer, Wall Connection04.7 430 M² Vapor Barrier, Reinforced Concrete Ceiling04.8 120 Linear Meters Of Vapor Barrier, Attika04.9 16 Pieces Of Vapor Barrier, Penetrations04.11 1 Psch Installation Plan04.12 430 M² Thermal Insulation, First Layer, Reinforced Concrete Ceiling Requirements Item 04.14 430 M² Gradient Insulation, Single Layer, Reinforced Concrete Ceiling 04.15 120 Linear Meters 04.15 Thermal Insulation, Parapet04.16 75 Linear Meters Of Thermal Insulation, Wall Connection 04.17 195 Linear Meters Of Insulation Wedges, 50 X 50 Mm 04.18 430 M² First Layer Of The Sealing, Reinforced Concrete Ceiling04.19 120 Running M First Layer Of Sealing, Parapet04.20 75 Running M First Layer Of Sealing, Wall Connection04.21 430 M² Second Layer Of Sealing, Reinforced Concrete Ceiling04.22 120 Running M Second Layer Of Sealing, Parapet04.23 75 Running M Second Layer Of Sealing, Wall Connection04.24 16 Pieces Of Bitumen Sealing, Penetrations04.25 120 Linear Meters Of Attic Cover05.1 90 M Of Hall Roof And Outbuildings Drainage05.2 15 M Of Drainage Of Floor-Level Elements06.1 15 Linear Meters Of Sealing Of Floor-Level Elements07.1 9 Pieces Of Sealing Of Floor Inlets08.1 12 Pieces Of Secure Reinforced Concrete Ceiling Hall Roof08.2 1 Piece Safety Harness (Ppe Set) Deliver08.3 1 Piece Metal Cabinet For Personal Protective Equipment, Wall Cabinet08.4 2 Pieces Single-Section Fixed Ladder Systems09.1 1 Hour Hourly Work Skilled Worker09.2 1 Hour Hourly Work Helper
|