1. The Subject Of The Order Is The Modernization Of The Pitch At The Municipal Primary School In Oława And Includes: • Demolition And Assembly Of The Pitch Fence, Playground And Pitch Equipment; • Removal Of The Artificial Grass Surface Of 1,500 M2 • Demolition And Removal Of The Existing Pitch Substructure • Construction Of A Drainage System For The Slab Sports Fields And Construction Of A Storm Sewage Connection With Connection To The Existing Rainwater In The Street. Warszawska• Execution Of The Substructure: - Sand Bedding Or Grit Sand Bed. 20 Cm - Crushed Stone, Fraction 4-31 Mm Thick, 15 Cm - Crushed Stone, Fraction 0-5 Mm Thick. 4 Cm• Laying A New Surface Made Of Artificial (Synthetic) Grass, Area 1500 M2o Required Technical Parameters Of Synthetic Grass Surfaces: - Fiber Height Min. 15 Mm Max. 25 Mm - Number Of Bunches Min. 20,900/M2 - Number Of Fibers Min. 40,000/M2 - Thickness Of Each Fiber Min. 110 Microns - Dtex Min 8,800 - Pulling Out A Tuft After Aging Min 41N - Pulling Out A Tuft Of Grass Before Aging Min 54 N - Surface Weight Min 2.1 Kg/M2 - Type Of Grass: 100% Polyethylene - Tufted Grass - Filling: Quartz Sand In Quantity Consistent With The Laboratory Test - Surface Color: Green, The Surface Should Be Laid In Accordance With With The Manufacturers Instructions - All Lines (White, Yellow, Red) Should Be Pasted Into The Surface, Do Not Paint. O Alternative Requirements For Artificial (Synthetic) Grass Surfaces - Type Of Grass: Woven, - Pile Height 15 Mm +/- 2 Mm, - Fiber Fleece: Polyethylene, Textured, Monofilament - Dtex Of The Bunch - Min. 11000 - Grass Fiber Mass Min. 1,200 G/M2, - Total Weight Min. 1800 G/M2, - Number Of Bunches - Min. 23,000/M2, - Number Of Filaments - Min. 370,000 Fibers/M2, - Lines - White, Yellow, Red, Pasted, - Filling: Quartz Sand. • Pasting Of Game Lines: 2 Basketball Courts, Handball Court, Volleyball Court • Installation Of Playground Equipment2. The Scope Of The Subject Matter Of The Contract On The Contractors Side Also Includes: • Compensation For Property Or Persons Resulting From The Work Carried Out, • Preparation Of A Work Schedule At The Investors Request And An Offer Cost Estimate, • Coverage Of Costs Related To The Use Of Water And Electricity, • Costs Related To The Implementation All Tests And Research Resulting From Standards And Legal Regulations, • Ensuring Constant Order And Cleanliness At The Construction Site, • Ensuring Appropriate Occupational Health And Safety Conditions, • Conducting And Paying For Surveying Services, • Preparing As-Built Documentation Together With Map3. A Detailed Description Of The Subject Of The Order Is Specified In: Design Documentation [Land Development Design, Reconstruction Design, Bill Of Quantities (Supporting Documents For Calculating The Offer Price), Bioz Information] And Technical Specifications For The Execution And Acceptance Of Construction Works Constituting Annexes To This Tor.
|